Theoretical background

Models overview

Overview of Models and processes which are used by eGo

eTraGo’s theoretical Background

Learn more about eTraGo’s theoretical background of methods and assumptions here.

eDisGo’s theoretical Background

Learn more about eTraGo’s theoretical background of methods and assumptions here.

eDisGo Cluster Method

In order to achieve acceptable computation times, the problem’s complexity can be reduced by applying a k-means cluster-algorithm to MV grids. The algorithm identifies a specified number of representative MV grids and assigns a weighting to each grid. As described here, the available clustering attributes are:

  • cumulative installed wind capacity,

  • cumulative installed solar capacity,

  • distance between transition point and farthest node of the MV grid

  • installed battery capacity (as a result of eTraGo’s investment optimization)

Subsequent to the MV grid simulations with the reduced number of representative grids, the cluster weighting is used to extrapolate the costs back to the original number of MV grids.

Economic calculation

The tool eGo unites the extra high (ehv) and high voltage (hv) models with the medium (mv) and low voltage (lv) models to ascertain the costs per selected measure and scenario. This results in a cross-grid-level economic result of the electrical grid and storage optimisation.

Overnight costs

The overnight costs represents the investment costs of the components or construction project without any interest, as if the project was completed “overnight”. The overnight costs (C_{\text{Overnight}} ) of the grid measures (lines and transformers) are calculated as:

C_{Line~extension}  = S_{Extension}~[MVA] * C_{assumtion}~[\frac{EUR}{MVA}] * L_{Line~length}~[km]

C_{Transformer~extension}   = S_{Extension}~[MVA] * C_{assumtion}~[\frac{EUR}{MVA}]

The total overnight grid extension costs are given by:

C_{overnight} = \sum C_{Line~extension} +  \sum C_{Transformer~extension}

The conversion of the given annuity costs of eTraGo is done in etrago_convert_overnight_cost().

Annuity costs

The annuity costs represents project investment costs with an interest as present value of an annuity. The investment years T and the interest rate p are defined as default in eGo with an interest rate ( p ) of 0.05 and a number of investment years ( T ) of 40 years. The values are based on the [StromNEV_A1] for the grid investment regulation in Germany.

The present value of an annuity (PVA) is calculated as:

PVA =  \frac{1}{p}- \frac{1}{\left ( p*\left (1 + p \right )^T \right )}

In order to calculate the C_{annuity} of a given period less than a year the annuity costs are factorized by the hours of the t_{year}=8760 and the defined calculation period.

t_{period} =  t_{\text{end\_snapshot}} - t_{\text{start\_snapshot}} ~[h]

The annuity costs ( C_{annuity} ) is calculated as:

C_{annuity} =   C_{\text{overnight}} * PVA * \left ( \frac{t_{year}}{\left ( t_{\text{period}}+ 1 \right )} \right )

Investment costs ehv/hv

The investment costs of the grid and storage expansion are taken from the studies [NEP2015a] for the extra and high voltage components and the [Dena]. The given costs are transformed in respect to PyPSA [€/MVA] format [PyPSA] components for the optimisation.

Overview of grid cost assumtions:

The table displays the transformer and line costs which are used for the calculation with eTraGo.

Table 1 Overview of grid cost assumtions

voltage level

component

capital costs

unit

source

110

AC overhead transmission lines

230

EUR/MVA

Dena 2012

220

AC overhead transmission lines

290

EUR/MVA

NEP 2015

380

AC overhead transmission lines

85

EUR/MVA

NEP 2015

DC

DC overhead transmission lines

375

EUR/MVA

NEP 2015

110/220

transformer

7500

EUR/MVA

Dena 2012

110/380

transformer

17333

EUR/MVA

NEP 2015

220/380

transformer

14166

EUR/MVA

NEP 2015

The eTraGo calculation of the annuity costs per simulation period is defined in set_line_costs() and set_trafo_costs().

Overview of storage cost assumtions:

Overview of eTraGo storage parameters and costs

Investment costs mv/lv

The tool eDisGO is calculating all grid expansion measures as capital or overnight costs. In order to get the annuity costs of eDisGo’s optimisation results the function edisgo_convert_capital_costs() is used. The cost assumption of [eDisGo] are taken from the [Dena] and [CONSENTEC] study. Based on the component the costs including earthwork costs can depend on population density according to [Dena].

References

[NEP2015a]

Übertragungsnetzbetreiber Deutschland. (2015). Netzentwicklungsplan Strom 2025 - Kostenschaetzungen, Version 2015, 1. Entwurf, 2015. (https://www.netzentwicklungsplan.de/sites/default/files/paragraphs-files/kostenschaetzungen_nep_2025_1_entwurf.pdf)

[Dena] (1,2,3)

dena Verteilnetzstudie. (2012). Ausbau- und Innovationsbedarf der Stromverteilnetze in Deutschland bis 2030. , Version 2015. (https://shop.dena.de/sortiment/detail/produkt/dena-verteilnetzstudie-ausbau-und-innovationsbedarf-der-stromverteilnetze-in-deutschland-bis-2030/)

[PyPSA]

PyPSA’s documentation (2018). Documentation of components. , Version v0.11.0. (https://pypsa.org/doc/components.html)

[StromNEV_A1]

Stromnetzentgeltverordnung - StromNEV Anlage 1 (2018). Verordnung über die Entgelte für den Zugang zu Elektrizitätsversorgungsnetzen (Stromnetzentgeltverordnung - StromNEV) Anlage 1 (zu § 6 Abs. 5 Satz 1) Betriebsgewöhnliche Nutzungsdauern. (https://www.gesetze-im-internet.de/stromnev/anlage_1.html)

[eDisGo]

eDisGo - grid expantion costs (2018). Cost assumption on mv and lv grid components. (https://github.com/openego/eDisGo/blob/dev/edisgo/config/config_grid_expansion_default.cfg#L85-L107)

[CONSENTEC]

CONSENTEC et.al (2006). Untersuchung der Voraussetzungen und möglicher Anwendung analytischer *Kostenmodelle in der deutschen Energiewirtschaft *. (https://www.bundesnetzagentur.de/SharedDocs/Downloads/DE/Sachgebiete/Energie/Unternehmen_Institutionen/Netzentgelte/Anreizregulierung/GA_AnalytischeKostenmodelle.pdf?__blob=publicationFile&v=1)